Executed Projects

eskayconstruction eskayconstruction

1. Client: M/S Bayer ABS

Nandesari, Dist: Baroda. Gujarat.

a. Volume of Work: PB Latex Project: Fabrication, Erection, Testing of CS, SS, GI & jacketed Piping, steel Structural work for housing equipment, Installation and alignment of equipment.

Completion Schedule: 6 months

b. Volume of work: PB Latex Expansion Project: Fabrication, Erection, Testing of CS, SS, GI & jacketed Piping, steel Structural work for housing equipment, Installation and alignment of equipment, Final hook up in shut down with existing plant.

Completion Schedule: 6 months

c. Volume of work: Fabrication and erection of 660 m3 Fire Water storage tank inclusive of railing ladder, fabrication of all nozzles, manhole, manhole covers, as per specifications and hydro testing / other testing of the same at site as per the spec. sheet.

Completion Schedule: 5 months.

eskayconstruction eskayconstruction

2. Client: M/S Bayer ABS

Katol, Dist: Panchmahal. Gujarat.

a. Volume of Work: SAN Project: Fabrication, Erection, Testing of CS, SS, GI & jacketed Piping, steel Structural work for housing equipment, Installation and alignment of equipment.

Completion Schedule: 6 months

b. Volume of Work: SAN Expansion Project: Fabrication, Erection, Testing of CS, SS, GI & jacketed Piping, steel Structural work for housing equipment, Installation and alignment of equipment, Final hook up in shut down with existing plant.

Completion Schedule: 3 months

eskayconstruction eskayconstruction

3. Client: M/S Bayer ABS

Moxi, Poicha, Dist: Baroda, Gujarat.

a. Volume of Work: Site Fabrication of 2 nos. 250 m3 Storage tanks including railing, ladder, nozzles, manhole, covers etc as per specifications.

Completion Schedule: 3 months

b. Volume of work: Fabrication and erection of steel work structures consisting of beams, angles, columns, chequered plates, asbestos roofing, rolled and compound sections, railings, walkways, stairsteps, platforms etc.

Completion Schedule: 3 months

c. Volume of work: Construction of steel structures for Solid storage area, compounding plant, Godown and other misc. works.

Completion Schedule: 1 months.

c. Volume of work: Dismantling 4 nos. silos, extension of same silos, re-erection and alignment.

Completion Schedule: 1 months.

eskayconstruction eskayconstruction eskayconstruction

4. Client: M/S Nuclear Power Corporation

(A Govt. of India Enterprise)KAIGA PROJECT Kaiga Site, Kaiga – 581400.Uttar Kannada, Karnataka.

a. Volume of Work: Handling, Transportation, Erection, Alignment, Welding, Inspection of Shuttle transport tubes, Pipe Supports & Stainless Steel penetration bellows, final testing of tubes & testing of Shuttle movement for units I and II.

Completion Schedule: 12 months

b. Volume of work: Handling, transportation, cleaning, fabrication, welding, erection inspection, and testing of vacuum mopping system and associated piping works.

Completion Schedule: 9 months

c. Volume of work: Fabrication and erection of supports for Fire protection system for SUT- I and SUT- II inclusive of Transportation, handling, fabrication of supports, CS welding, and supply and installation of Hilti fasteners.

Completion Schedule: 2 months.

d. Volume of work: Handling, Installation of feeder & header insulation cabinet and fabrication, erection and welding of feeder & header insulation cabinet and ventilation systems of Kaiga – II.

Completion Schedule: 12 months.

d. Volume of work: Handling, installation of storage bay equipments. Installation and welding of storage tray supports inside spent fuel storage bay.

Completion Schedule: 2 months.

eskayconstruction eskayconstruction eskayconstruction

5. M/S Bharat Starch Industries Ltd.

Patriot Complex, Opp. Amrakunj society, Race Course Circle, Baroda 390007.

a. Volume of Work: Handling, Transportation, Erection, Alignment, Welding, Inspection of Shuttle transport tubes, Pipe Supports & Stainless Steel penetration bellows, final testing of tubes & testing of Shuttle movement for units I and II.

Completion Schedule: 12 months

b. Volume of work: Handling, transportation, cleaning, fabrication, welding, erection inspection, and testing of vacuum mopping system and associated piping works.

Completion Schedule: 9 months

c. Volume of work: Fabrication and erection of supports for Fire protection system for SUT- I and SUT- II inclusive of Transportation, handling, fabrication of supports, CS welding, and supply and installation of Hilti fasteners.

Completion Schedule: 2 months.

d. Volume of work: Handling, Installation of feeder & header insulation cabinet and fabrication, erection and welding of feeder & header insulation cabinet and ventilation systems of Kaiga – II.

Completion Schedule: 12 months.

d. Volume of work: Handling, installation of storage bay equipments. Installation and welding of storage tray supports inside spent fuel storage bay.

Completion Schedule: 2 months.

eskayconstruction eskayconstruction eskayconstruction

6. Client: M/S Nuclear Power Corporation

(A Govt. of India Enterprise)KAIGA PROJECT Kaiga Site, Kaiga – 581400.Uttar Kannada, Karnataka.

a. Volume of Work: Handling, Transportation, Erection, Alignment, Welding, Inspection of Shuttle transport tubes, Pipe Supports & Stainless Steel penetration bellows, final testing of tubes & testing of Shuttle movement for units I and II.

Completion Schedule: 12 months

b. Volume of work: Handling, transportation, cleaning, fabrication, welding, erection inspection, and testing of vacuum mopping system and associated piping works.

Completion Schedule: 9 months

c. Volume of work: Fabrication and erection of supports for Fire protection system for SUT- I and SUT- II inclusive of Transportation, handling, fabrication of supports, CS welding, and supply and installation of Hilti fasteners.

Completion Schedule: 2 months.

d. Volume of work: Handling, Installation of feeder & header insulation cabinet and fabrication, erection and welding of feeder & header insulation cabinet and ventilation systems of Kaiga – II.

Completion Schedule: 12 months.

d. Volume of work: Handling, installation of storage bay equipments. Installation and welding of storage tray supports inside spent fuel storage bay.

Completion Schedule: 2 months.